SARATOGA SPRINGS — The following streets are to be paved according to the schedule below. Paving will begin at 6 a.m. and should be completed by 4 p.m. There is no parking of cars on the street during these hours, and driveway access/egress will be limited with potentially lengthy delays.
Monday, June 28
Mill Seward St. from Church St. to Pearl St.
Mill Long Alley from Walton St. to Dead End
Tuesday, June 29
Mill Morton Place from Nelson Ave. to Ludlow St.
Mill Fasig Lane from Nelson Ave. thru Ludlow St. to Dead End
Wednesday, June 30
Pave Seward St. from Church St. to Pearl St.
Pave Long Alley from Walton St to Dead End
Thursday, July 1
Pave Morton Place from Nelson Ave. to Ludlow St.
Pave Fasig Lane from Nelson Ave. thru Ludlow St. to Dead End