Paving Update: Week of August 17.
Driving through Saratoga Springs can be a challenge between large events, out of state drivers, and the inherent realities of going from a city of 30,000 people normally to 100,000 in the summer.
While those problems can’t be helped, avoiding areas of construction can be. Here is the paving update for the week of August 17.
• Monday, August 17: Trottingham Road will be milled from Hathorn Boulevard to Tamarack Trail — phase one of the project.
• Tuesday, August 18: Trottingham Road will be milled from Hathorn Boulevard to Tamarack Trail — phase one of the project.
• Tuesday, August 18: White Birch Path will be milled from Trottingham Road to Curt Boulevard.
• Wednesday, August 19: Trottingham Road will be paved from Hathorn Boulevard to Tamarack Trail — phase one of the project.
• Thursday, August 20: Trottingham Road will be paved from Hathorn Boulevard to Tamarack Trail — phase one of the project.
• Thursday, August 20: White Birch Path will be paved from Trottingham Road to Curt Boulevard.
Work on these days begins at 6:00 a.m. and is completed at 4:00 p.m. There is no street parking or through traffic on those days.